Consultancy Installation Stage
|
- Our façade engineer will inspect and monitor the quality of works as the installation progresses on site. Our engineer will also ensure that appropriate expertise and workforce is carrying out the installation works in line with the design details and specification. He will monitor and record the progress of works and discuss the findings in the site meetings. Any kind of deviations will be analysed and corrections will be recommended.
- On-site water test will be called for on completion of initial installation, to check the performance of the system after installation. The test will be witnessed by our engineer and any kind of failure shall be analysed and recommend the corrections.
- The on-site water test shall be called in three stages at the critical locations to verify the system performance.
- Also the pull out test for anchor fasteners will be called for and witnessed by our engineer before final go ahead given for the bracket installation. All the findings will be recorded and presented in the weekly meetings.
|
|
|
|
|
|
|
|